Cabinets went in today and they look great! Our original cabinet knobs are on backorder for 6 months so these will have to do for now!!
Monday, May 18, 2009
Saturday, May 16, 2009
Status update
All of the floors are down! Tile is grouted and Cabinets will go in on Monday!! It is moving along qutie fast! Trim is in the process of being put up and painted! I will get some more pictures tomorrow and pass them along!
A bit on the slow side.....
This house is in Chapel Hill and I have had pictures taken and on the computer to post for a while now, I just don't post them for some reason! Funny how something this close that I see a few times a week doesn't get as many posts as the River house did when we built it!! I will try to do better about posting...I just get in a hurry and live a fast paced life!!
Sunday, April 26, 2009
Friday, April 17, 2009
Tuesday, March 17, 2009
More Roof Framing!
They are almost ready to start putting the roof boards on! They have put on all of the front and back walls that were lacking!! It's starting to take some shape!!!
Thursday, March 12, 2009
Rafters
Rafters started going on this week...they will be ready for roofing hopefully by next Friday!